Project statuses for final registration

Modified on Fri, 17 May at 11:36 AM

Q: What are the different statuses for projects at final registration?


Cancelled: when the project has been awarded but the project contract has never been signed. Cancelled projects will not be visible in Annex 5 of the Final Programme Report, as the annex only lists contracted projects. 

Terminated: when the project contract has been terminated before the project reached its contracted end date.

Partially completed: when some but not all the planned activities in the project contract have been completed by its contracted end date.

Completed: when all the activities planned in the project have been completed.